Leominster Public Library
Expansion and Renovation Project

Friday, September 29, 2006

Construction 80% complete

The library project is now 80% complete. There is a lot happening both inside and outside the building.


A photo of the Pearl Street entrance taken this week .


Work has begun on the new parking lot. This is a view from the Pearl Street entrance looking into the parking lot that will be shared with the Pilgrim Congregationial Church.


A walkway is being installed along the side of the library.


The new transformer is being set into place on the side of the library.

The steps and landing leading into the 1910 building are nearing completion

The center skylight in the 1910 building has been reopened after almost fifty years.

The adult reference desk has been delivered and is being prepared to be set in place. Beyond it, you can see the wooden trim around the windows looking into the Cormier Center for Young Adults.